Hebbal Flyover

Key Facts

• FPCC Completed Hebbal flyover project in just 18 months.

• Length of corridor was 2340m.

• FPCC used 19K13 / 7K13 Prestressing System.

• FPCC has used 800 MT High tension strands.

• Project Status is completed.

 

 

Case Studies

Projects: Hebbal Flyover


Details: This bridge is located in Bangalore. The total length of flyover was 2.34 k.m.The number of segments was 785 nos and duration was 18 months. The 19K13/7K13 system was used. The contractor was Gammon India Ltd. and designer was Rites.

 